8 steps from start till finish


Let us explain

42
Weeks

Planning and sketching


Your vision is our mission

The duration of planning and sketching of the individual project lasts from three to four weeks. Together we understand your wishes and possibilities and we search for the most appropriate solutions.

3-4
Weeks

Technical project development


We adapt it to your specific needs

Log house drawing

Detailed and precise technical project development begins right away we have agreed with you about the capacity of the project, main costs and a vision of the outcome. Our architect creates precise technical project plans in six to eight weeks.

6-8
Weeks

Compilation and coordination of an estimate


We solve all questions

A compilation and coordination of an estimate usually lasts up to two weeks. After the coordination with you we start the most exciting process – manufacturing.

1-2
Weeks

The manufacturing process


You are welcome to visit us

The manufacturing process for an average size house project lasts from two to six weeks.  We are selective in our materials so we use only quality certified timber for our houses. If you are curious about the building process in KM Building factory, we welcome you to visit us and see how your new home takes shape.

2-6
Weeks

Log house drawing
Log house sauna
Nissehuset, Norway
Log house balcony

Transportation


We can handle any request

Log house drawing

A transportation to a construction site takes up to two weeks depending on the distance between the KM Building factory and the construction site.

1-2
Weeks

An assembly


Faster than you ever thought possible

The assembly of the house from wall construction, door and window installation to roofing, lasts from one to three weeks, depending on the complexity of the project.

1-3
Weeks

Log house drawing

Interior and exterior finish


Catch the excitement of your new home

Log house drawing

The exterior and interior finishes last up to three months for timber frame house and up to one month for log house, depending on your wishes and the amount of involved work.

Exterior finish includes windows and doors. Balconies finish. Log processing, painting, installation of gutters and installation of window and door trim.

Log house drawing

6-8
Weeks

Log house drawing

Interior finish Intermediate floor insulation, vapor barrier, floor- boards (pine), first floor insulation, painting, floor sanding, varnishing, installation of trims, interior doors and stairs and tiled floors in the bath- rooms.

Welcome to your new home


Experience the wonder of your new home